Solar + Battery Storage is a 2.5 MW solar+battery interconnection project in Bristol, Massachusetts with a current status of withdrawn. It is proposed to connect at The primary connection of the proposed project to Eversource Energy is located at the Wing Lane substation #624 Transformer #1 Line #240. The site is located approximately 0.26 circuit miles from Substation 624 near PSS/E node 111293(Wing Lane 13.2 KV).
Project facts
| Canonical name | Solar + Battery Storage |
|---|---|
| Queue ID | 1129 |
| Status | withdrawn |
| Source status | W |
| Market | SEMA |
| Technology | Solar+Battery |
| Capacity | 2.5 MW |
| State | Massachusetts |
| County | Bristol |
| Point of interconnection | The primary connection of the proposed project to Eversource Energy is located at the Wing Lane substation #624 Transformer #1 Line #240. The site is located approximately 0.26 circuit miles from Substation 624 near PSS/E node 111293(Wing Lane 13.2 KV) |
| Requested (queue) date | 2021-04-22 |
| Proposed in-service date | 2021-12-31 |
| Operational date | — |
| Withdrawn date | 2022-10-04 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata