Soluce Bravo Solar (28INR0269)

Soluce Bravo Solar is a 80.8 MW solar interconnection project in Brown, Texas with a current status of operational. It is proposed to connect at tap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2 .

80.8 MWCapacity
OperationalStatus
BrownMarket
SolarTechnology

Project facts

Canonical nameSoluce Bravo Solar
Queue ID28INR0269
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketBrown
TechnologySolar
Capacity80.8 MW
StateTexas
CountyBrown
Point of interconnectiontap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2
Requested (queue) date2025-01-13
Proposed in-service date
Operational date2029-09-17
Withdrawn date
DeveloperBNPB1, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.