State Line 439 161 kV Substation (ERAS-2025-034)

State Line 439 161 kV Substation is a 250.0 MW gas interconnection project in Joplin, Missouri with a current status of operational. It is proposed to connect at State Line 439 161 kV Substation.

250.0 MWCapacity
OperationalStatus
MOMarket
GasTechnology

Project facts

Canonical nameState Line 439 161 kV Substation
Queue IDERAS-2025-034
Statusoperational
Source statusERAS
MarketMO
TechnologyGas
Capacity250.0 MW
StateMissouri
CountyJoplin
Point of interconnectionState Line 439 161 kV Substation
Requested (queue) date2025-09-29
Proposed in-service date
Operational date2029-12-03
Withdrawn date
Developer
Utility / transmission ownerEMDE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.