Stem Solar (24INR0003)

Stem Solar is a 200.0 MW solar interconnection project in Swisher, Texas with a current status of operational. It is proposed to connect at tap 345kV 23914 Tule Canyon - 23912 Ogallala.

200.0 MWCapacity
OperationalStatus
SwisherMarket
SolarTechnology

Project facts

Canonical nameStem Solar
Queue ID24INR0003
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketSwisher
TechnologySolar
Capacity200.0 MW
StateTexas
CountySwisher
Point of interconnectiontap 345kV 23914 Tule Canyon - 23912 Ogallala
Requested (queue) date2020-02-04
Proposed in-service date
Operational date2025-08-26
Withdrawn date
DeveloperInnovative Solar 245, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.