Sunnymeade Road 13kV (AB1-099)

Sunnymeade Road 13kV is a 2.0 MW battery interconnection project in Somerset, New Jersey with a current status of withdrawn.

2.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameSunnymeade Road 13kV
Queue IDAB1-099
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity2.0 MW
StateNew Jersey
CountySomerset
Point of interconnection
Requested (queue) date2015-10-13
Proposed in-service date2016-09-01
Operational date
Withdrawn date2017-06-16
Developer
Utility / transmission ownerPSEG Long Island

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata