Sweetwater 345kV (GEN-2017-001)

Sweetwater 345kV is a 250.0 MW wind interconnection project in Custer, Nebraska with a current status of withdrawn. It is proposed to connect at Sweetwater 345kV.

250.0 MWCapacity
WithdrawnStatus
NEMarket
WindTechnology

Project facts

Canonical nameSweetwater 345kV
Queue IDGEN-2017-001
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologyWind
Capacity250.0 MW
StateNebraska
CountyCuster
Point of interconnectionSweetwater 345kV
Requested (queue) date2016-12-30
Proposed in-service date
Operational date
Withdrawn date2020-12-07
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.