SWENODA TAP - DUBLIN TAP - SS360 - 360WSM1 115.0kV (J3278)

SWENODA TAP - DUBLIN TAP - SS360 - 360WSM1 115.0kV is a 90.0 MW solar interconnection project in Swift, Minnesota with a current status of withdrawn. It is proposed to connect at SWENODA TAP - DUBLIN TAP - SS360 - 360WSM1 115.0kV.

90.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameSWENODA TAP - DUBLIN TAP - SS360 - 360WSM1 115.0kV
Queue IDJ3278
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity90.0 MW
StateMinnesota
CountySwift
Point of interconnectionSWENODA TAP - DUBLIN TAP - SS360 - 360WSM1 115.0kV
Requested (queue) date2024-04-16
Proposed in-service date2028-08-01
Operational date2028-08-01
Withdrawn date2025-12-23
Developer
Utility / transmission ownerGREAT RIVER ENERGY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.