Swift Air Solar (24INR0421)

Swift Air Solar is a 146.5 MW solar interconnection project in Ector, Texas with a current status of operational. It is proposed to connect at Tap 138kV 1019 Moss Switch – 11128 Shin Oak POD.

146.5 MWCapacity
OperationalStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameSwift Air Solar
Queue ID24INR0421
Statusoperational
Source statusoperational
MarketERCOT
TechnologySolar
Capacity146.5 MW
StateTexas
CountyEctor
Point of interconnectionTap 138kV 1019 Moss Switch – 11128 Shin Oak POD
Requested (queue) date2022-11-06
Proposed in-service date2025-08-06
Operational date2025-01-02
Withdrawn date
DeveloperSwift Solar LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.