Tap Fort Randall – Meadow Grove 230kV (GEN-2014-023)

Tap Fort Randall – Meadow Grove 230kV is a 79.9 MW wind interconnection project in Knox, Nebraska with a current status of withdrawn. It is proposed to connect at Tap Fort Randall – Meadow Grove 230kV.

79.9 MWCapacity
WithdrawnStatus
NEMarket
WindTechnology

Project facts

Canonical nameTap Fort Randall – Meadow Grove 230kV
Queue IDGEN-2014-023
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologyWind
Capacity79.9 MW
StateNebraska
CountyKnox
Point of interconnectionTap Fort Randall – Meadow Grove 230kV
Requested (queue) date2014-09-09
Proposed in-service date
Operational date
Withdrawn date2015-09-02
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata