Tazewell-Baileysville 138kV (U2-017)

Tazewell-Baileysville 138kV is a 200.0 MW wind interconnection project in Tazewell, Virginia with a current status of withdrawn.

200.0 MWCapacity
WithdrawnStatus
—Market
WindTechnology

Project facts

Canonical nameTazewell-Baileysville 138kV
Queue IDU2-017
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyWind
Capacity200.0 MW
StateVirginia
CountyTazewell
Point of interconnection—
Requested (queue) date2008-05-23
Proposed in-service date2011-07-01
Operational date—
Withdrawn date2008-10-30
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.