Thunder Bird 2 Gas (28INR0509)

Thunder Bird 2 Gas is a 1,273.8 MW gas interconnection project in Jack, Texas with a current status of operational. It is proposed to connect at Tap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443).

1,273.8 MWCapacity
OperationalStatus
JackMarket
GasTechnology

Project facts

Canonical nameThunder Bird 2 Gas
Queue ID28INR0509
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketJack
TechnologyGas
Capacity1,273.8 MW
StateTexas
CountyJack
Point of interconnectionTap Double circuit line between Jacksbro_5 (1429) to Willowck_5 (1421) and Jacksbro_5 (1429) to Hendrch_5 (1443)
Requested (queue) date2026-05-26
Proposed in-service date—
Operational date2031-06-14
Withdrawn date—
DeveloperKalnin Ventures, LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30phaseSS Started, FIS Started, No IASS Completed, FIS Started, No IAlow
2026-09-30operational_date—2031-06-14medium
2026-09-30proposed_online_date2031-06-14—medium
2026-09-30statusactiveoperationalhigh
2026-08-31new_project—activehigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.