TIMBER HILLS WIND (FKA HILLCREST WIND POWER 1) (554)

TIMBER HILLS WIND (FKA HILLCREST WIND POWER 1) is a 138.0 MW wind interconnection project in Shasta, California with a current status of withdrawn. It is proposed to connect at Pit River 1-Cottonwood 230kV.

138.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameTIMBER HILLS WIND (FKA HILLCREST WIND POWER 1)
Queue ID554
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyWind
Capacity138.0 MW
StateCalifornia
CountyShasta
Point of interconnectionPit River 1-Cottonwood 230kV
Requested (queue) date2010-02-01
Proposed in-service date
Operational date
Withdrawn date2011-10-03
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.