Shasta County, California — Interconnection Projects
The interXdata warehouse tracks 322 interconnection projects in Shasta, California, representing 3,935 MW of requested capacity.
322Total projects
1Active
314Operational
7Withdrawn
3,935 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 55 | 2,138 MW |
| Wind | 10 | 891 MW |
| Battery | 4 | 512 MW |
| Gas | 6 | 183 MW |
| Solar | 245 | 132 MW |
| Solar+Battery | 1 | 75 MW |
| Hydro | 1 | 4 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| ROUND MOUNTAIN WIND PROJECT | 437 | Wind | 350.0 MW | withdrawn | Shasta, California |
| CROSSROADS STORAGE | 1688 | Battery | 300.0 MW | withdrawn | Shasta, California |
| FOUNTAIN WIND | 1106 | Wind | 200.0 MW | withdrawn | Shasta, California |
| Shasta | 445_3 | Other | 142.0 MW | operational | Shasta, California |
| Shasta | 445_5 | Other | 142.0 MW | operational | Shasta, California |
| Shasta | 445_1 | Other | 142.0 MW | operational | Shasta, California |
| Shasta | 445_4 | Other | 142.0 MW | operational | Shasta, California |
| Shasta | 445_2 | Other | 142.0 MW | operational | Shasta, California |
| TIMBER HILLS WIND (FKA HILLCREST WIND POWER 1) | 554 | Wind | 138.0 MW | withdrawn | Shasta, California |
| CA Queue Project 2024-G2 — Solar in Shasta, California | 2024-G2 | Solar | 125.0 MW | active | Shasta, California |
| LAS HERMANAS BESS | 1276 | Battery | 110.0 MW | withdrawn | Shasta, California |
| HATCHET RIDGE WIND FARM PROJECT | 74 | Wind | 102.0 MW | operational | Shasta, California |
| Hatchet Ridge Wind Project | 56654_1 | Wind | 101.2 MW | operational | Shasta, California |
| ORIGIN ENERGY STORAGE | 1701 | Battery | 101.1 MW | withdrawn | Shasta, California |
| Spring Creek | 450_2 | Other | 90.0 MW | operational | Shasta, California |
| Spring Creek | 450_1 | Other | 90.0 MW | operational | Shasta, California |
| James B Black | 249_1 | Other | 85.1 MW | operational | Shasta, California |
| James B Black | 249_2 | Other | 83.5 MW | operational | Shasta, California |
| Judge F Carr | 442_2 | Other | 77.2 MW | operational | Shasta, California |
| Judge F Carr | 442_1 | Other | 77.2 MW | operational | Shasta, California |
| MEADOW RIDGE SOLAR AND BATTERY | 1860 | Solar+Battery | 75.0 MW | withdrawn | Shasta, California |
| Pit 7 | 270_H1 | Other | 57.6 MW | operational | Shasta, California |
| Pit 7 | 270_H2 | Other | 52.2 MW | operational | Shasta, California |
| Pit 4 | 267_1 | Other | 51.7 MW | operational | Shasta, California |
| Pit 4 | 267_2 | Other | 51.7 MW | operational | Shasta, California |
| Redding Power | 7307_6 | Gas | 42.5 MW | operational | Shasta, California |
| Redding Power | 7307_5 | Gas | 40.0 MW | operational | Shasta, California |
| Pit 6 | 269_H2 | Other | 39.6 MW | operational | Shasta, California |
| Pit 6 | 269_H1 | Other | 39.6 MW | operational | Shasta, California |
| Keswick | 443_1 | Other | 39.0 MW | operational | Shasta, California |
| Keswick | 443_3 | Other | 39.0 MW | operational | Shasta, California |
| Keswick | 443_2 | Other | 39.0 MW | operational | Shasta, California |
| Pit 5 | 268_H1 | Other | 38.2 MW | operational | Shasta, California |
| Pit 5 | 268_H2 | Other | 38.2 MW | operational | Shasta, California |
| Pit 1 | 265_H1 | Other | 34.6 MW | operational | Shasta, California |
| Pit 1 | 265_H2 | Other | 34.6 MW | operational | Shasta, California |
| Pit 5 | 268_H3 | Other | 33.2 MW | operational | Shasta, California |
| Pit 5 | 268_H4 | Other | 32.0 MW | operational | Shasta, California |
| Burney Forest Products | 10652_GEN1 | Other | 31.0 MW | operational | Shasta, California |
| SPI Anderson 2 | 59658_GEN1 | Other | 30.2 MW | operational | Shasta, California |
| Redding Power | 7307_3 | Gas | 27.9 MW | operational | Shasta, California |
| Redding Power | 7307_2 | Gas | 27.9 MW | operational | Shasta, California |
| Redding Power | 7307_4 | Gas | 26.8 MW | operational | Shasta, California |
| Pit 3 | 266_H2 | Other | 26.7 MW | operational | Shasta, California |
| Pit 3 | 266_H1 | Other | 26.7 MW | operational | Shasta, California |
| Pit 3 | 266_H3 | Other | 26.7 MW | operational | Shasta, California |
| Sierra Pacific Burney Facility | 50110_GEN1 | Other | 20.0 MW | operational | Shasta, California |
| Wheelabrator Shasta | 50881_GEN1 | Other | 18.3 MW | operational | Shasta, California |
| Wheelabrator Shasta | 50881_GEN2 | Other | 18.3 MW | operational | Shasta, California |
| Wheelabrator Shasta | 50881_GEN3 | Other | 18.3 MW | operational | Shasta, California |
| Redding Power | 7307_1 | Gas | 18.0 MW | operational | Shasta, California |
| Coleman PH | 227_1 | Other | 12.1 MW | operational | Shasta, California |
| Hat Creek 1 | 243_1 | Other | 10.0 MW | operational | Shasta, California |
| Hat Creek 2 | 244_1 | Other | 10.0 MW | operational | Shasta, California |
| Volta 1 | 290_1 | Other | 8.5 MW | operational | Shasta, California |
| Hatchet Creek Project | 10882_GEN1 | Other | 6.8 MW | operational | Shasta, California |
| Cove Hydroelectric | 10707_GEN1 | Other | 5.0 MW | operational | Shasta, California |
| Olsen | 50180_GEN1 | Other | 5.0 MW | operational | Shasta, California |
| Slate Creek | 50961_GEN1 | Other | 4.2 MW | operational | Shasta, California |
| West Queue Project 1055 — Hydro in Shasta, California | 1055 | Hydro | 4.2 MW | operational | Shasta, California |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| PowerHouse Solar, Inc. | 46 | 0 MW |
| Patterson & Patterson | 22 | 0 MW |
| HelioElectric | 16 | 0 MW |
| Top Hat Energy | 9 | 0 MW |
| Power House Solar | 9 | 0 MW |
| Glenn Tishue Electric Service | 8 | 0 MW |
| Helio Electric, Inc. | 7 | 0 MW |
| SPG Solar, Inc. | 6 | 0 MW |
| D&J Electric Inc. | 5 | 0 MW |
| Spectrum Energy Inc | 5 | 0 MW |
| Hydro-Stock, Inc. | 5 | 0 MW |
| Energy Efficiency Solar, Inc. dba ACRO Energy Inc. | 4 | 0 MW |
| Greg Tomsik Construction | 4 | 0 MW |
| IETS | 3 | 0 MW |
| M.D. Electric | 3 | 0 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: ca-dgstats; California ISO — public interconnection queue; U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; wapa-sn-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.