Tinker Air Force Base 138kV (GEN-2023-GR2)

Tinker Air Force Base 138kV is a 94.2 MW gas interconnection project in Oklahoma City, Oklahoma with a current status of active. It is proposed to connect at Tinker Air Force Base 138kV.

94.2 MWCapacity
ActiveStatus
OKMarket
GasTechnology

Project facts

Canonical nameTinker Air Force Base 138kV
Queue IDGEN-2023-GR2
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketOK
TechnologyGas
Capacity94.2 MW
StateOklahoma
CountyOklahoma City
Point of interconnectionTinker Air Force Base 138kV
Requested (queue) date2023-02-17
Proposed in-service date2026-05-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerOG&E

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata