TRAILWAYS ENERGY STORAGE (1706)

TRAILWAYS ENERGY STORAGE is a 101.2 MW battery interconnection project in Butte, California with a current status of withdrawn. It is proposed to connect at Paradise Substation 115kV.

101.2 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameTRAILWAYS ENERGY STORAGE
Queue ID1706
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyBattery
Capacity101.2 MW
StateCalifornia
CountyButte
Point of interconnectionParadise Substation 115kV
Requested (queue) date2020-04-15
Proposed in-service date
Operational date
Withdrawn date2020-07-15
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.