Butte County, California — Interconnection Projects
The interXdata warehouse tracks 494 interconnection projects in Butte, California, representing 2,574 MW of requested capacity.
494Total projects
2Active
481Operational
9Withdrawn
2,574 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Battery | 10 | 877 MW |
| Other | 18 | 776 MW |
| Solar | 449 | 533 MW |
| Solar+Battery | 2 | 310 MW |
| Wind | 4 | 60 MW |
| Gas | 11 | 18 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| CA Queue Project 2019-G1 — Solar in Butte, California | 2019-G1 | Solar | 300.0 MW | active | Butte, California |
| BULL RUN | 1852 | Solar+Battery | 225.0 MW | withdrawn | Butte, California |
| BULL RUN 2 ES | 1853 | Battery | 200.0 MW | withdrawn | Butte, California |
| STAGELINE ENERGY STORAGE | 1871 | Battery | 200.0 MW | withdrawn | Butte, California |
| Edward C Hyatt | 437_3 | Other | 117.0 MW | operational | Butte, California |
| Edward C Hyatt | 437_1 | Other | 117.0 MW | operational | Butte, California |
| Edward C Hyatt | 437_5 | Other | 117.0 MW | operational | Butte, California |
| TRAILWAYS ENERGY STORAGE | 1706 | Battery | 101.2 MW | withdrawn | Butte, California |
| CA Queue Project 2023-G4 — Solar in Butte, California | 2023-G4 | Solar | 100.0 MW | active | Butte, California |
| Edward C Hyatt | 437_4 | Battery | 97.7 MW | operational | Butte, California |
| Edward C Hyatt | 437_2 | Battery | 97.7 MW | operational | Butte, California |
| Edward C Hyatt | 437_6 | Battery | 97.7 MW | operational | Butte, California |
| CHICKAREE HYBRID SOLAR | 1686 | Solar+Battery | 85.0 MW | withdrawn | Butte, California |
| BUTTE SOLAR | 801 | Solar | 75.0 MW | withdrawn | Butte, California |
| Poe | 272_1 | Other | 71.4 MW | operational | Butte, California |
| Poe | 272_2 | Other | 71.4 MW | operational | Butte, California |
| Woodleaf | 419_1 | Other | 67.2 MW | operational | Butte, California |
| TRANSFER RIDGE WIND | 976 | Wind | 60.0 MW | withdrawn | Butte, California |
| Forbestown | 417_1 | Other | 41.9 MW | operational | Butte, California |
| Cresta | 231_1 | Other | 36.9 MW | operational | Butte, California |
| Cresta | 231_2 | Other | 36.9 MW | operational | Butte, California |
| Thermalito | 438_1 | Other | 32.6 MW | operational | Butte, California |
| Thermalito | 438_2 | Battery | 27.5 MW | operational | Butte, California |
| Thermalito | 438_4 | Battery | 27.5 MW | operational | Butte, California |
| Thermalito | 438_3 | Battery | 27.5 MW | operational | Butte, California |
| PANEM SOLAR | 1279 | Solar | 20.2 MW | withdrawn | Butte, California |
| MERIDIAN & MUNJAR SOLAR PROJECT | 657 | Solar | 20.0 MW | withdrawn | Butte, California |
| De Sabla | 232_1 | Other | 18.4 MW | operational | Butte, California |
| Forks of Butte Hydro Project | 50350_GEN1 | Other | 14.5 MW | operational | Butte, California |
| Sly Creek | 776_1 | Other | 12.1 MW | operational | Butte, California |
| Kelly Ridge | 418_1 | Other | 10.0 MW | operational | Butte, California |
| Centerville PH | 224_1 | Other | 5.5 MW | suspended | Butte, California |
| AMERESCO BUTTE COUNTY LANDFILL | 477 | Gas | 4.0 MW | operational | Butte, California |
| Butte College Main Campus Solar | 57970_SOL1 | Solar | 3.5 MW | operational | Butte, California |
| Thermalito Diverson Dam | 7129_TD1 | Other | 3.4 MW | operational | Butte, California |
| Gridley Main Two | 58371_GEN1 | Solar | 2.5 MW | operational | Butte, California |
| Ameresco Butte County | 57771_1 | Gas | 2.3 MW | operational | Butte, California |
| Sierra Nevada Brewing Co Hybrid | 58585_COGN | Gas | 2.0 MW | operational | Butte, California |
| Toadtown | 714_1 | Other | 1.8 MW | operational | Butte, California |
| Sierra Nevada Brewing Co Hybrid | 58585_SOLR | Solar | 1.7 MW | operational | Butte, California |
| Enloe Medical - Chico | 65210_ENL00 | Gas | 1.7 MW | operational | Butte, California |
| 2127 Harris Solar Project | 58919_2127 | Solar | 1.3 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN3 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN7 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN2 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN6 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN1 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN4 | Gas | 1.1 MW | operational | Butte, California |
| Oroville Cogeneration, LLC | 54477_GEN5 | Gas | 1.1 MW | operational | Butte, California |
| Gridley Main | 58370_GEN1 | Solar | 1.0 MW | operational | Butte, California |
| Centerville PH | 224_2 | Other | 0.9 MW | suspended | Butte, California |
| PG&E DG PGE-INT-113298719 | PGE-INT-113298719 | Solar | 0.8 MW | operational | Butte, California |
| PG&E DG PGE-INT-113287088 | PGE-INT-113287088 | Solar | 0.7 MW | operational | Butte, California |
| PG&E DG PGE-INT-113287112 | PGE-INT-113287112 | Solar | 0.6 MW | operational | Butte, California |
| PG&E DG PGE-INT-113287874 | PGE-INT-113287874 | Solar | 0.5 MW | operational | Butte, California |
| Sierra Nevada Brewing Co Hybrid | 58585_BESS | Battery | 0.5 MW | operational | Butte, California |
| PG&E DG PGE-INT-113301898 | PGE-INT-113301898 | Solar | 0.5 MW | operational | Butte, California |
| PG&E DG PGE-INT-113287561 | PGE-INT-113287561 | Solar | 0.4 MW | operational | Butte, California |
| PG&E DG PGE-INT-113302724 | PGE-INT-113302724 | Solar | 0.4 MW | operational | Butte, California |
| PG&E DG PGE-INT-113287114 | PGE-INT-113287114 | Solar | 0.3 MW | operational | Butte, California |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| SPG Solar, Inc. | 92 | 1 MW |
| Alternative Energy Systems, Inc. | 73 | 0 MW |
| Sun Light and Power | 44 | 0 MW |
| Chico Electric | 26 | 3 MW |
| Evergreen Wind, LLC | 22 | 0 MW |
| SunPower | 18 | 0 MW |
| Helio Power | 10 | 0 MW |
| St Clair Construction | 10 | 0 MW |
| PowerHouse Solar, Inc. | 8 | 0 MW |
| Real Goods | 7 | 0 MW |
| North Valley Systems Inc, DBA Sun Valley | 7 | 0 MW |
| California Solar Electric | 7 | 0 MW |
| Wing Solar & Wood Energy | 6 | 0 MW |
| Energy Efficiency Solar, Inc. dba ACRO Energy Inc. | 6 | 0 MW |
| ADVANCED SOLAR | 4 | 0 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: ca-dgstats; California ISO — public interconnection queue; U.S. EIA — Form EIA-860M generator inventory (operating + planned); wapa-sn-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Butte County.
Start tracking with interXdata