Triple B Solar Alt#2 (24INR0069)

Triple B Solar Alt#2 is a 150.0 MW solar interconnection project in Lampasas, Texas with a current status of operational. It is proposed to connect at Tap 138kV 7066 Adamsville - 7064 Lampasas.

150.0 MWCapacity
OperationalStatus
LampasasMarket
SolarTechnology

Project facts

Canonical nameTriple B Solar Alt#2
Queue ID24INR0069
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketLampasas
TechnologySolar
Capacity150.0 MW
StateTexas
CountyLampasas
Point of interconnectionTap 138kV 7066 Adamsville - 7064 Lampasas
Requested (queue) date2021-06-10
Proposed in-service date
Operational date2028-07-01
Withdrawn date
DeveloperTriple Line Solar
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.