Venado Wind (16INR0111)

Venado Wind is a 201.6 MW wind interconnection project in Starr, Texas with a current status of operational. It is proposed to connect at 8957 Lopeno 138kV.

201.6 MWCapacity
OperationalStatus
ERCOTMarket
WindTechnology

Project facts

Canonical nameVenado Wind
Queue ID16INR0111
Statusoperational
Source statusoperational
MarketERCOT
TechnologyWind
Capacity201.6 MW
StateTexas
CountyStarr
Point of interconnection8957 Lopeno 138kV
Requested (queue) date2015-05-17
Proposed in-service date2021-12-30
Operational date2021-12-06
Withdrawn date
DeveloperLas Lomas Wind Energy, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata