Wagener 115kV Substation (GEN-2021-048)

Wagener 115kV Substation is a 75.0 MW battery interconnection project in Lancaster, Nebraska with a current status of active. It is proposed to connect at Wagener 115kV Substation.

75.0 MWCapacity
ActiveStatus
NEMarket
BatteryTechnology

Project facts

Canonical nameWagener 115kV Substation
Queue IDGEN-2021-048
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketNE
TechnologyBattery
Capacity75.0 MW
StateNebraska
CountyLancaster
Point of interconnectionWagener 115kV Substation
Requested (queue) date2021-04-30
Proposed in-service date2029-09-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerLES

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.