Wakefield 230kV (GEN-2011-027)

Wakefield 230kV is a 120.0 MW wind interconnection project in Winside, Nebraska with a current status of operational. It is proposed to connect at Wakefield 230kV.

120.0 MWCapacity
OperationalStatus
NEMarket
WindTechnology

Project facts

Canonical nameWakefield 230kV
Queue IDGEN-2011-027
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketNE
TechnologyWind
Capacity120.0 MW
StateNebraska
CountyWinside
Point of interconnectionWakefield 230kV
Requested (queue) date2011-03-31
Proposed in-service date
Operational date2012-12-31
Withdrawn date
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata