Wallflower Energy Storage (30INR0093)

Wallflower Energy Storage is a 209.2 MW other interconnection project in Zapata, Texas with a current status of operational. It is proposed to connect at Tap the 345 kV Cenizo (#80225) - Del Sol (#80307) line.

209.2 MWCapacity
OperationalStatus
ZapataMarket
OtherTechnology

Project facts

Canonical nameWallflower Energy Storage
Queue ID30INR0093
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketZapata
TechnologyOther
Capacity209.2 MW
StateTexas
CountyZapata
Point of interconnectionTap the 345 kV Cenizo (#80225) - Del Sol (#80307) line
Requested (queue) date2026-02-25
Proposed in-service date
Operational date2029-12-30
Withdrawn date
DeveloperWallflower Energy Storage
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata