Walton Discover (aka Goat Rock) is a 150.0 MW gas interconnection project in Lee, Georgia with a current status of operational. It is proposed to connect at Goat Rock 230 kV Substation.
150.0 MWCapacity
OperationalStatus
SoutheastMarket
GasTechnology
Project facts
| Canonical name | Walton Discover (aka Goat Rock) |
|---|---|
| Queue ID | GI-020 |
| Status | operational |
| Source status | operational |
| Market | Southeast |
| Technology | Gas |
| Capacity | 150.0 MW |
| State | Georgia |
| County | Lee |
| Point of interconnection | Goat Rock 230 kV Substation |
| Requested (queue) date | 2023-12-31 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Georgia Transmission |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata