West Queue Project 778 — Solar+Battery in Emery, Utah

West Queue Project 778 — Solar+Battery in Emery, Utah is a 200.0 MW solar+battery interconnection project in Emery, Utah with a current status of operational. It is proposed to connect at Emery substation.

200.0 MWCapacity
OperationalStatus
WestMarket
Solar+BatteryTechnology

Project facts

Canonical nameWest Queue Project 778 — Solar+Battery in Emery, Utah
Queue ID778
Statusoperational
Source statusoperational
MarketWest
TechnologySolar+Battery
Capacity200.0 MW
StateUtah
CountyEmery
Point of interconnectionEmery substation
Requested (queue) date2016-07-13
Proposed in-service date2024-08-31
Operational date
Withdrawn date
DeveloperHornshadow Solar II, LLC
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata