Emery County, Utah — Interconnection Projects

The interXdata warehouse tracks 89 interconnection projects in Emery, Utah, representing 15,576 MW of requested capacity.

89Total projects
17Active
21Operational
49Withdrawn
15,576 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Battery276,198 MW
Solar+Battery223,700 MW
Solar283,050 MW
Other52,488 MW
Coal575 MW
Gas165 MW
Hydro11 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Huntington8069_2Other517.5 MWoperationalEmery, Utah
PACE Queue Project C2-22 — Battery in Emery, UtahC2-22Battery500.0 MWwithdrawnEmery, Utah
PACE Queue Project C3-065 — Battery in Emery, UtahC3-065Battery500.0 MWwithdrawnEmery, Utah
Huntington8069_1Other498.0 MWoperationalEmery, Utah
Hunter6165_3Other495.6 MWoperationalEmery, Utah
Hunter6165_1Other488.3 MWoperationalEmery, Utah
Hunter6165_2Other488.3 MWoperationalEmery, Utah
PACE Queue Project C1-11 — Solar+Battery in Emery, UtahC1-11Solar+Battery450.0 MWactiveEmery, Utah
PACE Queue Project C4-086 — Solar in Emery, UtahC4-086Solar450.0 MWwithdrawnEmery, Utah
PACE Queue Project C4-034 — Solar+Battery in Emery, UtahC4-034Solar+Battery400.0 MWwithdrawnEmery, Utah
West Queue Project 787 — Solar+Battery in Emery, Utah787Solar+Battery400.0 MWactiveEmery, Utah
Green River Energy Center - Hybrid67501_GRPVSolar400.0 MWoperationalEmery, Utah
PACE Queue Project T2-083 — Battery in Emery, UtahT2-083Battery400.0 MWactiveEmery, Utah
Green River Energy Center - Hybrid67501_GRBSBattery400.0 MWoperationalEmery, Utah
PACE Queue Project T2-052 — Solar+Battery in Emery, UtahT2-052Solar+Battery340.0 MWwithdrawnEmery, Utah
West Queue Project 1100 — Solar+Battery in Emery, Utah1100Solar+Battery250.0 MWwithdrawnEmery, Utah
Hornshadow Solar II, LLC67511_HS2LSolar200.0 MWoperationalEmery, Utah
PACE Queue Project S0037 — Battery in Emery, UtahS0037Battery200.0 MWactiveEmery, Utah
West Queue Project 778 — Solar+Battery in Emery, Utah778Solar+Battery200.0 MWoperationalEmery, Utah
West Queue Project 788 — Solar+Battery in Emery, Utah788Solar+Battery200.0 MWwithdrawnEmery, Utah
PACE Queue Project C4-062 — Battery in Emery, UtahC4-062Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS016 — Battery in Emery, UtahPIS016Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C3-002 — Battery in Emery, UtahC3-002Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C2-94 — Battery in Emery, UtahC2-94Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS082 — Battery in Emery, UtahPIS082Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C3-006 — Battery in Emery, UtahC3-006Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C4-064 — Battery in Emery, UtahC4-064Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS086 — Battery in Emery, UtahPIS086Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS014 — Battery in Emery, UtahPIS014Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C4-063 — Battery in Emery, UtahC4-063Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS013 — Battery in Emery, UtahPIS013Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C3-001 — Battery in Emery, UtahC3-001Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C4-065 — Battery in Emery, UtahC4-065Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS085 — Battery in Emery, UtahPIS085Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C2-96 — Battery in Emery, UtahC2-96Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS081 — Battery in Emery, UtahPIS081Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C2-95 — Battery in Emery, UtahC2-95Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C2-93 — Battery in Emery, UtahC2-93Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS015 — Battery in Emery, UtahPIS015Battery199.9 MWwithdrawnEmery, Utah
PACE Queue Project C3-005 — Battery in Emery, UtahC3-005Battery199.9 MWwithdrawnEmery, Utah
UT Queue Project PIS105 — Solar+Battery in Emery, UtahPIS105Solar+Battery199.0 MWactiveEmery, Utah
UT Queue Project PIS031 — Solar in Emery, UtahPIS031Solar199.0 MWwithdrawnEmery, Utah
West Queue Project 823 — Solar in Emery, Utah823Solar178.0 MWactiveEmery, Utah
UT Queue Project PIS056 — Solar in Emery, UtahPIS056Solar178.0 MWactiveEmery, Utah
UT Queue Project PIS021 — Solar in Emery, UtahPIS021Solar178.0 MWwithdrawnEmery, Utah
PACE Queue Project C2-99 — Solar+Battery in Emery, UtahC2-99Solar+Battery166.0 MWactiveEmery, Utah
PACE Queue Project T2-037 — Solar+Battery in Emery, UtahT2-037Solar+Battery150.0 MWactiveEmery, Utah
PACE Queue Project C2-64 — Solar+Battery in Emery, UtahC2-64Solar+Battery150.0 MWwithdrawnEmery, Utah
PACE Queue Project C3-040 — Solar+Battery in Emery, UtahC3-040Solar+Battery150.0 MWwithdrawnEmery, Utah
PACE Queue Project C2-167 — Solar in Emery, UtahC2-167Solar125.0 MWactiveEmery, Utah
UT Queue Project PIS057 — Solar in Emery, UtahPIS057Solar125.0 MWactiveEmery, Utah
UT Queue Project PIS017 — Solar in Emery, UtahPIS017Solar125.0 MWwithdrawnEmery, Utah
PACE Queue Project C1-14 — Solar+Battery in Emery, UtahC1-14Solar+Battery120.0 MWsuspendedEmery, Utah
PACE Queue Project S0015 — Battery in Emery, UtahS0015Battery100.0 MWactiveEmery, Utah
PACE Queue Project S0036 — Battery in Emery, UtahS0036Battery100.0 MWactiveEmery, Utah
West Queue Project 766 — Solar in Emery, Utah766Solar100.0 MWoperationalEmery, Utah
PACE Queue Project C2-113 — Solar+Battery in Emery, UtahC2-113Solar+Battery100.0 MWwithdrawnEmery, Utah
PACE Queue Project IS012 — Solar+Battery in Emery, UtahIS012Solar+Battery100.0 MWwithdrawnEmery, Utah
PACE Queue Project C3-012 — Solar+Battery in Emery, UtahC3-012Solar+Battery100.0 MWwithdrawnEmery, Utah
Hunter Solar LLC (UT)62656_HUSOLSolar100.0 MWoperationalEmery, Utah

Top developers

Developer (canonical)ProjectsCapacity
PacifiCorp6253 MW
Hornshadow Solar II, LLC2300 MW
Castle Solar, LLC140 MW
Hunter Solar, LLC1100 MW
Green River Solar I, LLC1400 MW
Pivot 13, LLC120 MW
Thayn Hydro LLC11 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Emery County.

Start tracking with interXdata