Western Kraft-Layfield 230 kV (J2489)

Western Kraft-Layfield 230 kV is a 140.0 MW battery interconnection project in Red River, Louisiana with a current status of withdrawn. It is proposed to connect at Western Kraft-Layfield 230 kV.

140.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameWestern Kraft-Layfield 230 kV
Queue IDJ2489
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity140.0 MW
StateLouisiana
CountyRed River
Point of interconnectionWestern Kraft-Layfield 230 kV
Requested (queue) date2022-09-14
Proposed in-service date2026-10-31
Operational date2026-10-31
Withdrawn date2023-03-25
Developer
Utility / transmission ownerCleco Power LLC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.