Wharton BESS (22INR0608)

Wharton BESS is a 10.0 MW battery interconnection project in Wharton, Texas with a current status of operational. It is proposed to connect at Property: 29.3134928 N, 96.1081571 W. Site is adjacent to Centerpoint substation. Station Name (TDSP Station Code): WR (Wharton)_x000D_ Load/Load Transformer Name:TR4_x000D_ PTI BUS number #43570 Voltage in kV (Transmission): 138 kV transmission voltage.

10.0 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameWharton BESS
Queue ID22INR0608
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity10.0 MW
StateTexas
CountyWharton
Point of interconnectionProperty: 29.3134928 N, 96.1081571 W. Site is adjacent to Centerpoint substation. Station Name (TDSP Station Code): WR (Wharton)_x000D_ Load/Load Transformer Name:TR4_x000D_ PTI BUS number #43570 Voltage in kV (Transmission): 138 kV transmission voltage
Requested (queue) date2022-11-08
Proposed in-service date2025-12-08
Operational date2025-12-18
Withdrawn date
DeveloperI-eye Storage LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata