Williams Creek Substation 230 (CSUT-2025-1)

Williams Creek Substation 230 is a 500.0 MW wind interconnection project in Lincoln, Colorado with a current status of operational. It is proposed to connect at Williams Creek Substation 230.

500.0 MWCapacity
OperationalStatus
COMarket
WindTechnology

Project facts

Canonical nameWilliams Creek Substation 230
Queue IDCSUT-2025-1
Statusoperational
Source statusDISIS STAGE
MarketCO
TechnologyWind
Capacity500.0 MW
StateColorado
CountyLincoln
Point of interconnectionWilliams Creek Substation 230
Requested (queue) date2025-03-03
Proposed in-service date
Operational date2027-12-31
Withdrawn date
Developer
Utility / transmission ownerCSU

Cross-source records

This project is also observed in: csu-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.