Wolf Ridge Repower (21INR0511)

Wolf Ridge Repower is a 9.0 MW wind interconnection project in Cooke, Texas with a current status of operational.

9.0 MWCapacity
OperationalStatus
ERCOTMarket
WindTechnology

Project facts

Canonical nameWolf Ridge Repower
Queue ID21INR0511
Statusoperational
Source statusoperational
MarketERCOT
TechnologyWind
Capacity9.0 MW
StateTexas
CountyCooke
Point of interconnection
Requested (queue) date2020-06-25
Proposed in-service date
Operational date2023-10-10
Withdrawn date
Developer
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.