Wynne East to Wynne South 161kV line (J1125 sub) (J1723)

Wynne East to Wynne South 161kV line (J1125 sub) is a 10.0 MW battery interconnection project in Cross, Arkansas with a current status of withdrawn. It is proposed to connect at Wynne East to Wynne South 161kV line (J1125 sub).

10.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameWynne East to Wynne South 161kV line (J1125 sub)
Queue IDJ1723
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity10.0 MW
StateArkansas
CountyCross
Point of interconnectionWynne East to Wynne South 161kV line (J1125 sub)
Requested (queue) date2021-11-02
Proposed in-service date2023-04-01
Operational date2023-04-01
Withdrawn date2022-08-05
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.