Bradley County, Arkansas — Interconnection Projects
The interXdata warehouse tracks 5 interconnection projects in Bradley, Arkansas, representing 536 MW of requested capacity.
5Total projects
0Active
1Operational
4Withdrawn
536 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 5 | 536 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| AECC Hermitage south- Hilo 115Kv | J2977 | Solar | 150.0 MW | withdrawn | Bradley, Arkansas |
| AECC Hermitage South-Hilo 115kV | J2862 | Solar | 150.0 MW | withdrawn | Bradley, Arkansas |
| AECC HERMITAGE SOUTH - HILO 115.0kV | J2639 | Solar | 105.8 MW | operational | Bradley, Arkansas |
| MISO Queue Project J661 — Solar in Bradley, Arkansas | J661 | Solar | 90.0 MW | withdrawn | Bradley, Arkansas |
| MISO Queue Project J377 — Solar in Bradley, Arkansas | J377 | Solar | 40.0 MW | withdrawn | Bradley, Arkansas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.