The interXdata warehouse tracks 15 interconnection projects in Phillips, Arkansas, representing 2,583 MW of requested capacity.
15Total projects
1Active
7Operational
7Withdrawn
2,583 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 12 | 2,125 MW |
| Wind | 2 | 258 MW |
| Other | 1 | 200 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| GILLETT - ELAINE 115.0kV | J4196 | Solar | 300.0 MW | withdrawn | Phillips, Arkansas |
| RITCHIE SWYD - TARLETON 230.0kV | J3802 | Solar | 300.0 MW | withdrawn | Phillips, Arkansas |
| AECC AUBREY - RITCHIE SWYD 230.0kV | J3270 | Solar | 250.0 MW | withdrawn | Phillips, Arkansas |
| AECC AUBREY - RITCHIE SWYD 230.0kV | J3893 | Solar | 214.0 MW | withdrawn | Phillips, Arkansas |
| Ritchie Plant 230 kV Substation | S1074 | — | 200.0 MW | operational | Phillips, Arkansas |
| Taping 'AECC Aubrey / 6AUBREY# (338885)' to 'Ritchie SES Switchyard / 6RITCHIE-2! (337991)' 230kV Li | J3116 | Solar | 200.0 MW | withdrawn | Phillips, Arkansas |
| Long Lake Solar, LLC | 66649_LLS | Solar | 200.0 MW | operational | Phillips, Arkansas |
| RITCHIE SWYD - TARLETON 230.0kV | J2750 | Solar | 197.5 MW | operational | Phillips, Arkansas |
| RITCHIE SWYD - TARLETON 230.0kV | J3292 | Wind | 193.0 MW | operational | Phillips, Arkansas |
| BALD KNOB T.E.T.C. P.S. #6 SS - AECC COFFEEVILLE 161.0kV | J3812 | Solar | 158.6 MW | withdrawn | Phillips, Arkansas |
| AECC AUBREY-RITCHIE SES SWITCHYARD 230 KV | J2456 | Solar | 100.0 MW | operational | Phillips, Arkansas |
| Barton - West Helena 115kV | J3112 | Solar | 100.0 MW | operational | Phillips, Arkansas |
| Ritchie Plant Substation 230kV | J3141 | Solar | 100.0 MW | operational | Phillips, Arkansas |
| RITCHIE SWYD - TARLETON 230.0kV | J3374 | Wind | 65.0 MW | withdrawn | Phillips, Arkansas |
| SR West Helena | 68570_WHELN | Solar | 4.8 MW | active | Phillips, Arkansas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Phillips County.
Start tracking with interXdata