Poinsett County, Arkansas — Interconnection Projects
The interXdata warehouse tracks 11 interconnection projects in Poinsett, Arkansas, representing 1,891 MW of requested capacity.
11Total projects
0Active
3Operational
8Withdrawn
1,891 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 9 | 1,701 MW |
| Battery | 2 | 190 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Marked Tree 161 kV | J2386 | Solar | 300.0 MW | withdrawn | Poinsett, Arkansas |
| TRUMANN - HARRISBURG SS 161.0kV | J3569 | Solar | 300.0 MW | withdrawn | Poinsett, Arkansas |
| MARKED TREE - TWIST 161.0kV | J3571 | Solar | 250.0 MW | withdrawn | Poinsett, Arkansas |
| HARRISBURG SS - HARRISBURG 161.0kV | J3373 | Solar | 200.0 MW | withdrawn | Poinsett, Arkansas |
| HARRISBURG | J3969 | Solar | 196.0 MW | withdrawn | Poinsett, Arkansas |
| AECC TRUMANN WEST - TRUMANN 161.0kV | J3536 | Solar | 190.0 MW | withdrawn | Poinsett, Arkansas |
| Harrisburg 161 kV Substation | J2928 | Solar | 160.0 MW | withdrawn | Poinsett, Arkansas |
| MARKED TREE | J4174 | Battery | 140.0 MW | operational | Poinsett, Arkansas |
| Newport - Fisher 161 kV Line | J2773 | Solar | 100.0 MW | operational | Poinsett, Arkansas |
| Marked Tree 161 kV | J2521 | Battery | 50.0 MW | withdrawn | Poinsett, Arkansas |
| SR Fisher | 68101_FISHR | Solar | 4.8 MW | operational | Poinsett, Arkansas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.