Mesa County, Colorado — Interconnection Projects
The interXdata warehouse tracks 14 interconnection projects in Mesa, Colorado, representing 310 MW of requested capacity.
14Total projects
3Active
10Operational
1Withdrawn
310 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 8 | 162 MW |
| Battery | 1 | 100 MW |
| Gas | 1 | 27 MW |
| Other | 4 | 21 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Grand Valley Solar Generation and BESS | 68343_GRVA2 | Battery | 100.0 MW | active | Mesa, Colorado |
| Grand Valley Solar Generation and BESS | 68343_GRVA1 | Solar | 100.0 MW | active | Mesa, Colorado |
| West Queue Project GI-2016-28 — Solar in Mesa, Colorado | GI-2016-28 | Solar | 51.8 MW | withdrawn | Mesa, Colorado |
| Fruita | 471_1 | Gas | 26.6 MW | operational | Mesa, Colorado |
| Upper Molina | 521_1 | Other | 9.9 MW | operational | Mesa, Colorado |
| Lower Molina | 520_1 | Other | 5.6 MW | operational | Mesa, Colorado |
| Vinelands Power Plant | 68234_GEN1 | Other | 4.5 MW | operational | Mesa, Colorado |
| Pivot Solar 57 LLC | 70206_PS57 | Solar | 2.0 MW | active | Mesa, Colorado |
| USS Fruita Solar LLC CSG | 66432_USGBS | Solar | 2.0 MW | operational | Mesa, Colorado |
| Mesa PV1 | 59199_MESA1 | Solar | 1.6 MW | operational | Mesa, Colorado |
| Mesa CSG 2 Massicotte | 62718_X0037 | Solar | 1.5 MW | operational | Mesa, Colorado |
| Mesa CSG 1 Murdock | 62719_X0038 | Solar | 1.5 MW | operational | Mesa, Colorado |
| Oak Leaf Solar XXXI LLC (CSG) | 62244_53977 | Solar | 1.5 MW | operational | Mesa, Colorado |
| Redlands Water & Power | 50267_RED1 | Other | 1.4 MW | operational | Mesa, Colorado |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Mesa County.
Start tracking with interXdata