Metcalfe County, Kentucky — Interconnection Projects
The interXdata warehouse tracks 18 interconnection projects in Metcalfe, Kentucky, representing 2,691 MW of requested capacity.
18Total projects
2Active
3Operational
13Withdrawn
2,691 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 15 | 1,305 MW |
| Other | 2 | 1,280 MW |
| Solar+Battery | 1 | 106 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Southeast Queue Project 57 — Other in Metcalfe, Kentucky | 57 | Other | 640.0 MW | withdrawn | Metcalfe, Kentucky |
| Southeast Queue Project 132 — Other in Metcalfe, Kentucky | 132 | Other | 640.0 MW | withdrawn | Metcalfe, Kentucky |
| Summer Shade 161 kV | AG2-684 | Solar | 331.0 MW | withdrawn | Metcalfe, Kentucky |
| PJM Queue Project AG2-094 — Solar in Metcalfe, Kentucky | AG2-094 | Solar | 150.0 MW | withdrawn | Metcalfe, Kentucky |
| Summer Shade-Green County 161 kV | AG2-094 - moved to TC2 | Solar | 150.0 MW | withdrawn | Metcalfe, Kentucky |
| Summer Shade Solar | AG1-341 | Solar+Battery | 106.0 MW | active | Metcalfe, Kentucky |
| Summer Shade 161 kV | AG1-341 - moved to TC1 | Solar | 106.0 MW | active | Metcalfe, Kentucky |
| Summer Shade - Green County 161 kV | AH1-083 - moved to TC2 | Solar | 100.0 MW | withdrawn | Metcalfe, Kentucky |
| PJM Queue Project AH1-083 — Solar in Metcalfe, Kentucky | AH1-083 | Solar | 100.0 MW | withdrawn | Metcalfe, Kentucky |
| Knob Lick 69kV | AH1-081 - moved to TC2 | Solar | 60.0 MW | withdrawn | Metcalfe, Kentucky |
| PJM Queue Project AH1-081 — Solar in Metcalfe, Kentucky | AH1-081 | Solar | 60.0 MW | withdrawn | Metcalfe, Kentucky |
| Glover Creek Solar, LLC | 66047_GLOVE | Solar | 55.0 MW | operational | Metcalfe, Kentucky |
| Knob Lick-JB Galloway Tap 69 kV | AG2-598 | Solar | 50.0 MW | withdrawn | Metcalfe, Kentucky |
| PJM Queue Project AH1-082 — Solar in Metcalfe, Kentucky | AH1-082 | Solar | 44.0 MW | withdrawn | Metcalfe, Kentucky |
| Knob Lick 69kV | AH1-082 - moved to TC2 | Solar | 44.0 MW | withdrawn | Metcalfe, Kentucky |
| Patton Rd-Summer Shade 69 kV | AE2-071 | Solar | 35.0 MW | operational | Metcalfe, Kentucky |
| Patton Rd-Summer Shade 69 kV | AF1-203 | Solar | 20.0 MW | operational | Metcalfe, Kentucky |
| Patton Rd-Summer Shade 69 kV | AI2-327 | Solar | 0.0 MW | withdrawn | Metcalfe, Kentucky |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Coneflower Solar 2 LLC | 2 | 250 MW |
| Wildrye Solar LLC | 2 | 104 MW |
| Summer Shade Solar, LLC | 1 | 106 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Metcalfe County.
Start tracking with interXdata