Wabasha County, Minnesota — Interconnection Projects
The interXdata warehouse tracks 18 interconnection projects in Wabasha, Minnesota, representing 762 MW of requested capacity.
18Total projects
0Active
17Operational
1Withdrawn
762 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Battery | 2 | 450 MW |
| Solar | 14 | 309 MW |
| Other | 2 | 3 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Wabaco | J3848 | Battery | 250.0 MW | operational | Wabasha, Minnesota |
| Wabaco to Alma 161 kV Tap | J2600 | Solar | 245.0 MW | withdrawn | Wabasha, Minnesota |
| North Rochester - Briggs Road 345.0kV | J2601 | Battery | 200.0 MW | operational | Wabasha, Minnesota |
| Lake City (A) to Zumbro Falls (B) | J2867 | Solar | 50.0 MW | operational | Wabasha, Minnesota |
| Wabasha Holdco Solar CSG | 60838_WABAS | Solar | 3.0 MW | operational | Wabasha, Minnesota |
| Rochester Hydro | 2007_1 | Other | 1.3 MW | operational | Wabasha, Minnesota |
| Rochester Hydro | 2007_2 | Other | 1.3 MW | operational | Wabasha, Minnesota |
| Carina Community Solar | 61179_JCCS1 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| MN CSG 2019-105 | 68373_HAGER | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| DIVOCSG 14 LLC | 68457_DIV14 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Carina Community Solar | 61179_JCCS4 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| SolarClub 20 LLC | 65451_SC 20 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Carina Community Solar | 61179_JCCS3 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Carina Community Solar | 61179_JCCS2 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| DIVOCSG 13 | 68412_DIV13 | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Novel Sunnyfield Farms Solar LLC CSG | 64483_SNYFD | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Wabasha Solar | 62800_WAB | Solar | 1.0 MW | operational | Wabasha, Minnesota |
| Pepin Garden | 66577_MNC02 | Solar | 0.9 MW | operational | Wabasha, Minnesota |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.