Banner County County, Nebraska — Interconnection Projects
The interXdata warehouse tracks 4 interconnection projects in Banner County, Nebraska, representing 521 MW of requested capacity.
4Total projects
1Active
0Operational
3Withdrawn
521 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 4 | 521 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| NE Queue Project 2017-G3 — Wind in Banner County, Nebraska | 2017-G3 | Wind | 250.0 MW | withdrawn | Banner County, Nebraska |
| Roundtop - Stegall 115- | 2017-G2 | Wind | 130.0 MW | active | Banner County, Nebraska |
| Laramie River Station - Sidney 345kV | GEN-2016-034 | Wind | 90.0 MW | withdrawn | Banner County, Nebraska |
| NE Queue Project 2010-G1 — Wind in Banner County, Nebraska | 2010-G1 | Wind | 51.0 MW | withdrawn | Banner County, Nebraska |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue; wapa-rm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Banner County County.
Start tracking with interXdata