Bertie County, North Carolina — Interconnection Projects
The interXdata warehouse tracks 39 interconnection projects in Bertie, North Carolina, representing 2,164 MW of requested capacity.
39Total projects
6Active
8Operational
25Withdrawn
2,164 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 33 | 2,008 MW |
| Battery | 5 | 144 MW |
| Gas | 1 | 12 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Cashie 230 kV | AD1-132 | Solar | 150.0 MW | withdrawn | Bertie, North Carolina |
| Earleys-Cashie 230 kV | AG1-312 | Solar | 140.0 MW | withdrawn | Bertie, North Carolina |
| Earleys 230kV | AC2-063 | Solar | 100.0 MW | withdrawn | Bertie, North Carolina |
| PJM Queue Project AG1-438 — Solar in Bertie, North Carolina | AG1-438 | Solar | 100.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-Earleys 230 kV | AG1-438 - moved to TC1 | Solar | 100.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-Earleys 230 kV | AG1-437 - moved to TC1 | Solar | 100.0 MW | withdrawn | Bertie, North Carolina |
| PJM Queue Project AG1-437 — Solar in Bertie, North Carolina | AG1-437 | Solar | 100.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-Trowbridge 230 kV | AD1-022 | Solar | 80.0 MW | active | Bertie, North Carolina |
| Cashie 230 kV | AD2-184 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AE1-025 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AD2-183 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AE1-026 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AE1-024 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-E. Trowbridge 230kV | AA1-136 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AD2-185 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Earleys-Everetts 230kV | AA1-135 | Solar | 80.0 MW | withdrawn | Bertie, North Carolina |
| Earleys-Everetts 230 kV | AE2-037 | Solar | 71.5 MW | withdrawn | Bertie, North Carolina |
| PJM Queue Project AG2-382 — Solar in Bertie, North Carolina | AG2-382 | Solar | 70.0 MW | active | Bertie, North Carolina |
| Cashie 230 kV | AG2-382 - moved to TC2 | Solar | 70.0 MW | active | Bertie, North Carolina |
| Cashie-Earleys 230kV | AC2-158 | Solar | 65.0 MW | withdrawn | Bertie, North Carolina |
| Cashie 230 kV | AH1-271 - moved to TC2 | Solar | 40.0 MW | active | Bertie, North Carolina |
| PJM Queue Project AH1-271 — Solar in Bertie, North Carolina | AH1-271 | Solar | 40.0 MW | active | Bertie, North Carolina |
| Cashie-Trowbridge 230 kV | AD1-023 | Solar | 40.0 MW | withdrawn | Bertie, North Carolina |
| PJM Queue Project AG1-442 — Battery in Bertie, North Carolina | AG1-442 | Battery | 35.0 MW | withdrawn | Bertie, North Carolina |
| PJM Queue Project AG1-443 — Battery in Bertie, North Carolina | AG1-443 | Battery | 35.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-Earleys 230 kV | AG1-442 - moved to TC1 | Battery | 35.0 MW | withdrawn | Bertie, North Carolina |
| Cashie-Earleys 230 kV | AG1-443 - moved to TC1 | Battery | 35.0 MW | withdrawn | Bertie, North Carolina |
| Kelford (Duke) | 59527_KELF1 | Solar | 20.0 MW | operational | Bertie, North Carolina |
| Kelford 34.5kV | W3-050 | Solar | 20.0 MW | withdrawn | Bertie, North Carolina |
| Kelford 34.5kV | Z2-043 | Solar | 20.0 MW | operational | Bertie, North Carolina |
| Tunis 34.5 kV | AG1-036 | Solar | 13.5 MW | withdrawn | Bertie, North Carolina |
| Kelford 115kV | R93 | Gas | 12.0 MW | withdrawn | Bertie, North Carolina |
| Kelford (Cypress) | 59796_FLS1 | Solar | 5.0 MW | operational | Bertie, North Carolina |
| Lewiston Solar | 59174_5MWPV | Solar | 5.0 MW | operational | Bertie, North Carolina |
| Windsor Solar | 59171_5MWPV | Solar | 5.0 MW | operational | Bertie, North Carolina |
| Windsor Cooper HIill Solar, LLC | 58847_1 | Solar | 5.0 MW | operational | Bertie, North Carolina |
| Windsor Hwy 17 Solar | 64678_WDH17 | Solar | 5.0 MW | operational | Bertie, North Carolina |
| Windsor BESS | 69872_BAT1 | Battery | 3.9 MW | active | Bertie, North Carolina |
| Kelford 34.5kV | AA1-072 | Solar | 3.1 MW | operational | Bertie, North Carolina |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| RWE Solar Development, LLC | 4 | 270 MW |
| Merry Hill PV I, LLC | 2 | 110 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Bertie County.
Start tracking with interXdata