Carroll County, Ohio — Interconnection Projects

The interXdata warehouse tracks 13 interconnection projects in Carroll, Ohio, representing 5,598 MW of requested capacity.

13Total projects
2Active
5Operational
6Withdrawn
5,598 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas85,230 MW
Solar4288 MW
Solar+Battery180 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
PJM Queue Project AH1-680 — Gas in Carroll, OhioAH1-680Gas1,300.0 MWactiveCarroll, Ohio
Sammis - South Canton 345 kVAH1-680 - moved to TC2Gas1,300.0 MWactiveCarroll, Ohio
Sammis–Star 345kVY2-085Gas1,050.0 MWwithdrawnCarroll, Ohio
Tidd–Canton CentralY2-050Gas742.0 MWoperationalCarroll, Ohio
Carroll County Energy59773_SGT1Gas361.3 MWoperationalCarroll, Ohio
Carroll County Energy59773_CGT2Gas235.5 MWoperationalCarroll, Ohio
Carroll County Energy59773_CGT1Gas235.5 MWoperationalCarroll, Ohio
PJM Queue Project AH1-551 — Solar in Carroll, OhioAH1-551Solar100.0 MWwithdrawnCarroll, Ohio
Carrollton Solar 138 kVAH2-275Solar100.0 MWwithdrawnCarroll, Ohio
Echelon SolarAH1-526Solar+Battery80.0 MWwithdrawnCarroll, Ohio
Knox - Washington CEC 138 kVAH1-526 - moved to TC2Solar80.0 MWwithdrawnCarroll, Ohio
Bane 69 kVAH1-236Solar8.0 MWwithdrawnCarroll, Ohio
Stemple 345kVAC2-016Gas6.0 MWoperationalCarroll, Ohio

Top developers

Developer (canonical)ProjectsCapacity
Chestnut Run Energy LLC11,300 MW
Echelon Solar LLC180 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Carroll County.

Start tracking with interXdata