Stonewall County, Texas — Interconnection Projects
The interXdata warehouse tracks 7 interconnection projects in Stonewall, Texas, representing 1,666 MW of requested capacity.
7Total projects
3Active
3Operational
1Withdrawn
1,666 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 5 | 1,396 MW |
| Other | 1 | 135 MW |
| Battery | 1 | 135 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Moccasin Solar | 26INR0269 | Solar | 603.6 MW | operational | Stonewall, Texas |
| Swenson Solar | 70135_SWNSN | Solar | 600.0 MW | active | Stonewall, Texas |
| Stonewall BESS | 28INR0253 | Other | 135.0 MW | operational | Stonewall, Texas |
| Stonewall BESS | 68666_RIC88 | Battery | 135.0 MW | active | Stonewall, Texas |
| PV New Glory | 23INR0377 | Solar | 72.5 MW | withdrawn | Stonewall, Texas |
| Stonewall Solar | 27INR0242 | Solar | 60.2 MW | operational | Stonewall, Texas |
| Stonewall Solar | 67562_RIC92 | Solar | 60.2 MW | active | Stonewall, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Swenson Solar LLC | 1 | 604 MW |
| PREMIER ENGINEERING USA CORP. | 1 | 72 MW |
| Stonewall ESS, LLC | 1 | 135 MW |
| Stonewall PV, LLC | 1 | 60 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Stonewall County.