Sevier County, Utah — Interconnection Projects
The interXdata warehouse tracks 14 interconnection projects in Sevier, Utah, representing 1,776 MW of requested capacity.
14Total projects
2Active
2Operational
10Withdrawn
1,776 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Battery | 2 | 580 MW |
| Gas | 1 | 525 MW |
| Coal | 1 | 270 MW |
| Solar | 6 | 261 MW |
| Solar+Battery | 2 | 100 MW |
| Other | 2 | 40 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| West Queue Project 403 — Gas in Sevier, Utah | 403 | Gas | 525.0 MW | withdrawn | Sevier, Utah |
| PACE Queue Project C3-152 — Battery in Sevier, Utah | C3-152 | Battery | 500.0 MW | withdrawn | Sevier, Utah |
| West Queue Project 121 — Coal in Sevier, Utah | 121 | Coal | 270.0 MW | withdrawn | Sevier, Utah |
| PACE Queue Project C3-143 — Solar+Battery in Sevier, Utah | C3-143 | Solar+Battery | 80.0 MW | withdrawn | Sevier, Utah |
| West Queue Project 602 — Solar in Sevier, Utah | 602 | Solar | 80.0 MW | withdrawn | Sevier, Utah |
| Sigurd Solar LLC | 62666_SGSOL | Solar | 80.0 MW | operational | Sevier, Utah |
| PACE Queue Project S0016 — Battery in Sevier, Utah | S0016 | Battery | 80.0 MW | active | Sevier, Utah |
| West Queue Project 589 — Solar in Sevier, Utah | 589 | Solar | 80.0 MW | operational | Sevier, Utah |
| PACE Queue Project C4-003 — Other in Sevier, Utah | C4-003 | Other | 20.0 MW | withdrawn | Sevier, Utah |
| PACE Queue Project T2-004 — Other in Sevier, Utah | T2-004 | Other | 20.0 MW | active | Sevier, Utah |
| PACE Queue Project C3-093 — Solar+Battery in Sevier, Utah | C3-093 | Solar+Battery | 19.9 MW | withdrawn | Sevier, Utah |
| PACE Queue Project C3-094 — Solar in Sevier, Utah | C3-094 | Solar | 19.9 MW | withdrawn | Sevier, Utah |
| West Queue Project 625 — Solar in Sevier, Utah | 625 | Solar | 1.0 MW | withdrawn | Sevier, Utah |
| West Queue Project 546 — Solar in Sevier, Utah | 546 | Solar | 0.5 MW | withdrawn | Sevier, Utah |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Sigurd Solar, LLC | 1 | 80 MW |
| South Valley Sustainability Park | 1 | 1 MW |
| PacifiCorp | 1 | 270 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Sevier County.
Start tracking with interXdata