Unknown County, Virginia — Interconnection Projects
The interXdata warehouse tracks 26 interconnection projects in Unknown, Virginia, representing 2,111 MW of requested capacity.
26Total projects
0Active
16Operational
10Withdrawn
2,111 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 4 | 1,867 MW |
| Solar | 16 | 135 MW |
| Other | 6 | 109 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Broadford-Jackson Ferry Phase II 765kV | Z1-078 | Gas | 777.0 MW | withdrawn | Unknown, Virginia |
| Broadford-Jackson's Ferry 765kV | Y2-058 | Gas | 762.0 MW | withdrawn | Unknown, Virginia |
| Oak Hall 138 kV (Oil CT) | A02 | Gas | 315.0 MW | operational | Unknown, Virginia |
| West Point | U2-056 | Other | 88.7 MW | withdrawn | Unknown, Virginia |
| Oak Hall | W1-005 | Solar | 20.0 MW | operational | Unknown, Virginia |
| Oak Hall | W1-006 | Solar | 20.0 MW | operational | Unknown, Virginia |
| East Mill 138kV | Y1-068 | Other | 20.0 MW | operational | Unknown, Virginia |
| Chickahominy 34.5kV | AB1-135 | Solar | 20.0 MW | withdrawn | Unknown, Virginia |
| East Lima-South Kenton 138kV | W1-037 | Solar | 20.0 MW | withdrawn | Unknown, Virginia |
| Oak Hall | W1-004 | Solar | 20.0 MW | operational | Unknown, Virginia |
| Oak Hall | W1-003 | Solar | 20.0 MW | operational | Unknown, Virginia |
| Culpeper 34.5kV | AB1-152 | Solar | 15.0 MW | withdrawn | Unknown, Virginia |
| Winchester 34.5 kV | P27 | Gas | 13.0 MW | operational | Unknown, Virginia |
| Mt. Storm-Doubs 500kV | T47 | Other | 0.0 MW | withdrawn | Unknown, Virginia |
| Oak Hall D | AA1-028 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall A | AA1-025 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall | Z1-102 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall B | AA1-026 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall | Z1-101 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall | Z1-103 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall | Z1-100 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Oak Hall C | AA1-027 | Solar | 0.0 MW | operational | Unknown, Virginia |
| Bristers Ox 500kV | Z2-017 | Other | — | operational | Unknown, Virginia |
| Meadow Brook | U3-005 | Other | — | withdrawn | Unknown, Virginia |
| Meadow Brook 500kV | U2-088 | Other | — | withdrawn | Unknown, Virginia |
| Boykin 115kV | Z2-100 | Solar | — | withdrawn | Unknown, Virginia |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.