City of Hamilton - (OH) — Interconnection Queue Projects

City of Hamilton - (OH) is associated with 9 tracked interconnection projects representing 194 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

9Projects
0Active
9Operational
0Withdrawn
194 MWRequested capacity
1Markets

Capacity by technology

TechnologyProjectsRequested capacity
Other8177 MW
Gas116 MW

Portfolio by market

MarketProjects
PJM9

Geographic footprint

StateProjects
Ohio6
Kentucky3

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Meldahl Hydroelectric Project56872_3Other35.0 MWoperationalBracken, Kentucky
Meldahl Hydroelectric Project56872_1Other35.0 MWoperationalBracken, Kentucky
Meldahl Hydroelectric Project56872_2Other35.0 MWoperationalBracken, Kentucky
Greenup Hydro4258_1Other23.4 MWoperationalScioto, Ohio
Greenup Hydro4258_2Other23.4 MWoperationalScioto, Ohio
Greenup Hydro4258_3Other23.4 MWoperationalScioto, Ohio
Hamilton (OH)2917_GT2Gas16.3 MWoperationalButler, Ohio
Hamilton Hydro7807_4Other1.1 MWoperationalButler, Ohio
Hamilton Hydro7807_3Other1.1 MWoperationalButler, Ohio

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.