NEETSW — Interconnection Queue Projects

NEETSW is associated with 8 tracked interconnection projects representing 2,374 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

8Projects
1Active
1Operational
6Withdrawn
2,374 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Solar61,870 MW
Wind1300 MW
Battery1204 MW

Geographic footprint

StateProjects
Kansas4
New Mexico4

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Crossroads - Hobbs 345 kV SubstationGEN-2024-073Solar500.0 MWwithdrawnLea, New Mexico
Crossroads-Hobbs-Roadrunner 345 kV LineGEN-2024-124Solar420.0 MWwithdrawnLea, New Mexico
Wolf Creek - Blackberry 345 kV LineGEN-2024-258Wind300.0 MWwithdrawnAllen, Kansas
Wolf Creek - Blackberry 345 kV LineGEN-2024-139Solar250.0 MWwithdrawnCoffey, Kansas
Crossroads - Hobbs 345kV LinesGEN-2024-262Solar250.0 MWwithdrawnLea, New Mexico
Crossroads - Hobbs 345kV LinesGEN-2024-263Solar250.0 MWwithdrawnLea, New Mexico
Wolf Creek - Blackberry 345 kV SubstationGEN-2020-090Battery204.3 MWactiveBourbon, Kansas
Wolf Creek - Blackberry 345 kV LineGEN-2024-287Solar199.8 MWoperationalCrawford, Kansas

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Track queue activity connecting through NEETSW.