Black Mountain Energy Storage II — Interconnection Portfolio
Black Mountain Energy Storage II is associated with 15 tracked interconnection projects representing 4,980 MW of requested capacity.
Entity resolution: this developer rolls up 2 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 2 | 2,972 MW |
| Other | 11 | 1,499 MW |
| Battery | 2 | 509 MW |
Portfolio by market
| Market | Projects |
|---|---|
| ERCOT | 8 |
Geographic footprint
| State | Projects |
|---|---|
| Texas | 13 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| BM Great Rock Energy Center | 30INR0091 | Gas | 1,981.2 MW | operational | Leon, Texas |
| BM Freestone Energy Center | 29INR0298 | Gas | 990.6 MW | operational | Freestone, Texas |
| Barbers Hill BESS | 24INR0495 | Battery | 307.7 MW | withdrawn | — |
| Great Rock BESS | 25INR0230 | Other | 300.9 MW | operational | Leon, Texas |
| Goldeneye BESS | 25INR0100 | Other | 201.6 MW | operational | Bell, Texas |
| Outer Loop BESS | 23INR0382 | Other | 201.2 MW | operational | Harris, Texas |
| Moonshine Hill BESS | 24INR0435 | Other | 201.2 MW | withdrawn | Harris, Texas |
| Yellow Rose BESS | 26INR0338 | Battery | 201.0 MW | withdrawn | — |
| Canvasback BESS | 25INR0160 | Other | 150.5 MW | withdrawn | Calhoun, Texas |
| Picadillo BESS | 24INR0275 | Other | 100.8 MW | operational | Martin, Texas |
| Goldeneye II BESS | 25INR0158 | Other | 100.8 MW | withdrawn | Bell, Texas |
| Hana Springs BESS | 24INR0494 | Other | 100.8 MW | operational | Lampasas, Texas |
| Canvasback II BESS | 25INR0454 | Other | 50.4 MW | withdrawn | Calhoun, Texas |
| Mallard BESS II | 25INR0137 | Other | 50.4 MW | withdrawn | Collin, Texas |
| City Breeze II BESS | 25INR0496 | Other | 40.4 MW | withdrawn | Matagorda, Texas |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Provenance: ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Monitor Black Mountain Energy Storage II's portfolio across all markets.
Start tracking with interXdata