ARDILLA (2049)

ARDILLA is a 400.0 MW battery interconnection project in Riverside, California with a current status of withdrawn. It is proposed to connect at Devers Substation 230kV.

400.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameARDILLA
Queue ID2049
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyBattery
Capacity400.0 MW
StateCalifornia
CountyRiverside
Point of interconnectionDevers Substation 230kV
Requested (queue) date2021-04-15
Proposed in-service date
Operational date
Withdrawn date2025-10-02
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata