Cachi BESS (22INR0388)

Cachi BESS is a 205.5 MW battery interconnection project in Guadalupe, Texas with a current status of operational. It is proposed to connect at 7680 Clear Springs 138kV.

205.5 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameCachi BESS
Queue ID22INR0388
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity205.5 MW
StateTexas
CountyGuadalupe
Point of interconnection7680 Clear Springs 138kV
Requested (queue) date2020-08-20
Proposed in-service date2025-09-16
Operational date2025-04-30
Withdrawn date
DeveloperBRP Cachi BESS LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata