Cherry Sage Storage 1 SLF (28INR0359)

Cherry Sage Storage 1 SLF is a 150.3 MW solar+battery interconnection project in Concho, Texas with a current status of active. It is proposed to connect at (#60423) TREADWELL 138kV..

150.3 MWCapacity
ActiveStatus
ERCOTMarket
Solar+BatteryTechnology

Project facts

Canonical nameCherry Sage Storage 1 SLF
Queue ID28INR0359
Statusactive
Source statusactive
MarketERCOT
TechnologySolar+Battery
Capacity150.3 MW
StateTexas
CountyConcho
Point of interconnection(#60423) TREADWELL 138kV.
Requested (queue) date2025-04-25
Proposed in-service date2029-02-23
Operational date
Withdrawn date
DeveloperCherry Sage Storage 1 LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.