Concho Pearl Solar and Storage (67956_CONBS)

Concho Pearl Solar and Storage is a 162.4 MW battery interconnection project in Concho, Texas with a current status of active.

162.4 MWCapacity
ActiveStatus
ERCOMarket
BatteryTechnology

Project facts

Canonical nameConcho Pearl Solar and Storage
Queue ID67956_CONBS
Statusactive
Source status(T) Regulatory approvals received. Not under construction
MarketERCO
TechnologyBattery
Capacity162.4 MW
StateTexas
CountyConcho
Point of interconnection
Requested (queue) date
Proposed in-service date2027-10-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerRed River Clean Energy

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.