Falfur BESS (24INR0593)

Falfur BESS is a 9.8 MW battery interconnection project in Brooks, Texas with a current status of operational. It is proposed to connect at Connected to AEP 12.47kV Station Name (TDSP Station Code): FALFUR Load/Load Transformer Name: R1 PTI Bus Number: #8510 Voltage in kV (Transmission Level): 138kV.

9.8 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameFalfur BESS
Queue ID24INR0593
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity9.8 MW
StateTexas
CountyBrooks
Point of interconnectionConnected to AEP 12.47kV Station Name (TDSP Station Code): FALFUR Load/Load Transformer Name: R1 PTI Bus Number: #8510 Voltage in kV (Transmission Level): 138kV
Requested (queue) date2023-06-27
Proposed in-service date2025-08-06
Operational date2025-02-03
Withdrawn date
DeveloperRegis Falfurrias LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.