GOLDEN FIELDS SOLAR 3 (1213)

GOLDEN FIELDS SOLAR 3 is a 100.0 MW solar interconnection project in Kern, California with a current status of withdrawn. It is proposed to connect at Whirlwind 230 kV substation.

100.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameGOLDEN FIELDS SOLAR 3
Queue ID1213
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar
Capacity100.0 MW
StateCalifornia
CountyKern
Point of interconnectionWhirlwind 230 kV substation
Requested (queue) date2015-04-30
Proposed in-service date
Operational date
Withdrawn date2015-07-08
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata